Many of you will have been keeping a close eye on the emergency repair works to the West Works timber structure at the entrance to Littlehampton Harbour over the past few weeks.
We are pleased to report that the project has been successfully completed and that contractor demobilisation is now underway.
Despite some particularly challenging weather conditions, including recent storms, the works were delivered safely, quickly and to an exceptionally high standard. Littlehampton Harbour Board would like to thank Teignmouth Maritime Services, their workforce and all those involved for their professionalism, expertise and commitment throughout the project. We’d also like to thank local residents, businesses and harbour users for their patience and understanding while these essential repairs were carried out.
As many will appreciate, the urgency of these emergency works meant that Littlehampton Harbour Board had no option but to postpone the planned shingle recycling operation from Shoal Bank within the harbour entrance.
With the repair project now complete and contractors leaving site, attention will turn to this important follow-on operation.
Over the past year, significant volumes of shingle have accumulated within the harbour entrance, resulting in substantial growth of Shoal Bank and reducing navigable depths. To maintain safe access to the harbour, a shingle recycling and dredging operation will commence in early December.
Approximately 15,000 tonnes of shingle will be recovered from the harbour entrance and recycled for beneficial use, including beach replenishment projects within the local area. The works will also reduce the large volume of shingle currently stored within the first bay of West Beach, helping to improve access to the foreshore and maximise the time before natural coastal processes return material to the harbour entrance.
The operation will involve excavators, haulage vehicles and associated plant working from West Beach for approximately three weeks. Public access to the beach will be maintained throughout, with appropriate fencing, traffic management and safety measures in place.